  • Crews are finishing installing the final seats. Just a reminder that there are 21”, 22”, and 23” seats organized throughout the PAC so that no one sits directly behind the person in front of them. 
  • Contractors will be installing the pit filler next week.
  • Inspectors will be on-site to inspect the two PAC lifts (elevators) this week. The required phone line to each lift has been installed.
  • Stage lighting installation has started this week and will take 2-3 weeks to complete.
  • Crews are busy doing audio/visual work. Speakers have been installed and there is a lot of other sound and light control equipment to install on stage and in the control room.
  • As shown in the attached picture, the stage floor has been installed. The floor will be painted the week of December 22nd (after the pit filler is installed).
  • Electricians are working on electrical work, part of which is installing the isle lights on the seats.
  • Painters are working on spaces in and around the PAC.
  • Much of the flooring has been installed inside the PAC, including isles and pit. Carpet on the west hallway is being installed today and walk-off carpet will be installed in and around the activity entrances/exits.
  • Expected completion – End of January 2021PACPAC
Posted by jsimmonds  On Jan 27, 2021 at 10:42 AM 1 Comment
  

BAC (Benson Activity Center):

  • Electricians are completing rough ins.
  • Plumbers have completed rough-ins for bathrooms.
  • Ventilation crews have installed ducts and rough-ins. Insolation is being installed on ductwork.
  • Sheeting will be installed on the dividing wall, with mudding and taping to follow.
  • On ground RTU is scheduled to be installed toward the end of December.
  • Exterior doors are expected to be installed the week of December 14th.
  • Epoxy floor is scheduled to be poured the first week in January. 
  • Steel contractor will be installing an 8’ high steel liner around the interior of the facility to protect the insulation.
  • Expected completion – Mid-End of January 2021
Posted by jsimmonds  On Jan 27, 2021 at 10:25 AM
  

The window replacement project at BHS is underway. Photo of the new compared to old windows.

Lighting for the parking lot has been installed along with surveillance cameras for the parking lots.

 