Art & Band Rooms Transitioning to New Classrooms 

Art Room Change:  Art teacher Jenessa Grossman transitioned to a new classroom (room 412) at the beginning of second semester. The kiln has been set and wired right outside the room in the welding shop, outlets have been wired in the room, cabinets removed, projector mounted, and countertop and sinks removed from the current art room and installed into the new art location.

 

Old Art Room:  Band will move into the current art room during the time of the auditorium construction. The move will begin once Art is situated in the new room.

 

Current Auditorium:  The tentative plan is to demolish the auditorium before the 2019-2020 school year begins. We are discussing options for the ALC location. With the plan to demolish the auditorium this coming summer, we want to have everything moved out of that space before the end of the school year.

 

Builders Risk Insurance:  From the on-going category of “we don’t know, what we don’t know”. School districts need to carry Builders Risk Insurance both to cover on-site materials as well as “Soft Cost” Risk Insurance. Dave and I are working with the district insurance broker to secure insurance for these areas.

 

Bond Funds:  Bond Funds were received on December 6th and have been invested with PFM. Following the initial draw schedule, the funds have been invested in a mix of short and long term accounts. Liquidity is important so the district has funds to pay invoices as they come in, but invest long term to maximize return. School Districts are very restricted in where funds can be invested.

 

Gym Remodel:  Contracts are being prepared and contractors have ordered performance/payment bonds and insurance certifications. Pending the final building permit, contractors should be ready to go on the gym remodel the week of December 17th.

 

Posted by On 28 March, 2019 at 1:38 PM  

 