Benson Activity Center 

BAC (Benson Activity Center):

  • Electricians are completing rough ins.
  • Plumbers have completed rough-ins for bathrooms.
  • Ventilation crews have installed ducts and rough-ins. Insolation is being installed on ductwork.
  • Sheeting will be installed on the dividing wall, with mudding and taping to follow.
  • On ground RTU is scheduled to be installed toward the end of December.
  • Exterior doors are expected to be installed the week of December 14th.
  • Epoxy floor is scheduled to be poured the first week in January. 
  • Steel contractor will be installing an 8’ high steel liner around the interior of the facility to protect the insulation.
  • Expected completion – Mid-End of January 2021