BAC (Benson Activity Center):
- Electricians are completing rough ins.
- Plumbers have completed rough-ins for bathrooms.
- Ventilation crews have installed ducts and rough-ins. Insolation is being installed on ductwork.
- Sheeting will be installed on the dividing wall, with mudding and taping to follow.
- On ground RTU is scheduled to be installed toward the end of December.
- Exterior doors are expected to be installed the week of December 14th.
- Epoxy floor is scheduled to be poured the first week in January.
- Steel contractor will be installing an 8’ high steel liner around the interior of the facility to protect the insulation.
- Expected completion – Mid-End of January 2021