Performing Arts Center 
  • Crews are finishing installing the final seats. Just a reminder that there are 21”, 22”, and 23” seats organized throughout the PAC so that no one sits directly behind the person in front of them. 
  • Contractors will be installing the pit filler next week.
  • Inspectors will be on-site to inspect the two PAC lifts (elevators) this week. The required phone line to each lift has been installed.
  • Stage lighting installation has started this week and will take 2-3 weeks to complete.
  • Crews are busy doing audio/visual work. Speakers have been installed and there is a lot of other sound and light control equipment to install on stage and in the control room.
  • As shown in the attached picture, the stage floor has been installed. The floor will be painted the week of December 22nd (after the pit filler is installed).
  • Electricians are working on electrical work, part of which is installing the isle lights on the seats.
  • Painters are working on spaces in and around the PAC.
  • Much of the flooring has been installed inside the PAC, including isles and pit. Carpet on the west hallway is being installed today and walk-off carpet will be installed in and around the activity entrances/exits.
  • Expected completion – End of January 2021PACPAC
Posted by jsimmonds On 27 January, 2021 at 10:42 AM  1 Comment

Comments
Helaine Bolter (Guest) said On 03 February, 2022 at 9:32 AM
Attempting to purchase tickets for February 20   
Leave Your Comment
Security Measure
 
Website by SchoolMessenger Presence. © 2024 SchoolMessenger Corporation. All rights reserved.