NS Construction in Progress, BHS Expected to Begin in Early October 

Northside Construction:

·       Footings have been poured for the NS cafeteria/activity space and kitchen.  Crews plan to pour masonry walls Friday.  Once those are poured Kennedy will backfill and put in fill so plumbing can be installed and the floor can get poured. 

·       NS office work will begin next week. Mary’s office has been rearranged to accommodate the temp wall that will be installed for construction. Demolition work of the NS men’s and women’s bathrooms is scheduled to begin as soon as the cafeteria floor is poured. Crews will access the bathrooms from the outside.

·       The rain has slowed the soil correction on the west end addition, in fact seven days of digging have been lost so far. However, the plan is to resume digging on Friday and get back on schedule.  

·       October 16-18 Kennedy and the city plan to dig in the new wastewater and storm water lines in the front of NS.  The two small trees will be relocated to the back of NS, unfortunately the larger trees are too big to move.  This will involve digging up part of the SW entrance sidewalk and out onto the street. 

·       Temporary power has been installed at both construction sites at NS.

 

BHS

·       Bids have been awarded for the BHS construction project. Contracts have been sent out. Contractors are working on shop drawings and ordering materials.

·       Construction at BHS is expected to begin in early October.

NS Construction 9-16-19

Posted by On 19 September, 2019 at 1:50 PM  

 